Food sector company rolls out a 32 million euro investment programme in production area in less than 12 months

The Oobeya methodology for project management and early equipment management ensure compliance with start-up deadlines and budget targets, guaranteeing equipment reliability and efficiency from the very beginning.

32M€ investment
<1 year implementation lead time
100% of preventive and autonomous maintenance schedules met
100% of critical spare parts available in warehouse
100% of staff assigned to the facility trained
Contact us

NEEDS

  • To roll out a productive investment programme of more than 30 million euros.
  • To produce a product for sale in standard manufacturing conditions within 11 months.
  • To meet the initial budget.

IMPROVEMENT PROCESS

  • Setting up a multidisciplinary project team: Engineering, Production, Maintenance,
  • Prevention and Quality.
  • Designing and constructing the Oobeya Room.
  • Drawing up a meetings schedule: daily (project team) and weekly (Management Committee).
  • Defining monitoring indicators.
  • Developing the FMEA process.
  • Standardising production processes and staff training.
  • Standardising the process for the launch of new equipment.
caso exito

Related methodologies

See methodologies

Improving the effectiveness of plant and facilities

Based on people involvement in process control and systematic reduction in breakdowns.
See more